Tuesday, 19 October 2010

“The Record” on our project

The Parish magazine "The Record" of the local Anglican Parish of St Mary-the-Virgin, Kenton, has dedicated a whole page on our sacred project.

The Parish Priest, Fr. Giles Pinnock, had recently visited our new Church, where Fr. Anastasios had welcomed him and showed him around. He was very impressed by our endeavours and decided to write an article for his Parish magazine.

Monday, 18 October 2010

Photo of the week - 54

We had good progress this week and very visible too.

The main Dome is slowly-slowly becoming coppered, the dome of the Bell Tower was covered with certain layers of wood and red tiles are now appearing on the timber roof.

Friday, 15 October 2010

Live on the Church roof

A photograph has obviously great impact and it is regarded as equal to 1000 words. A video though is even better, as it shows moving pictures and come present a whole area or a story in a very graphic way.


Thus, we thought of taking a short video today, showing what happens up on our new Church’s roof and how it looks at this moment.

Thursday, 14 October 2010

The windows

The first windows have now been fixed.

They had been here with us for quite a while, but their time has just come now to be put in place.

They were made by a company called BLAIRS, which operates up in Scotland.

They actually look beautiful and fit very nicely on both our Bell Tower and on various walls.

Soon they will all be put in place, thus securing the Church even better.

Wednesday, 13 October 2010

Copper on Dome

The copper is being at the moment fixed on the main Dome.

Preparations are done in the interior of our new Church; then our specialist engineers take the leaves of copper up on the Dome.

The weather is quite chilly today and working up there must be a real testing.

But the professionalism and dedication of our engineers and workers should be praised and commended.

Now our high Dome began to shine from far away.

Tuesday, 12 October 2010

Tiles on the roof

At the end of last week the crane put the red tiles on the roof of our new Church.

Our dedicated workes started then distributing them on the specific areas where they should go.

Then, from yesterday they started laying and fixing them in their place.

Monday, 11 October 2010

Photo of the week - 53

53 pictures of the week so far. This week, apart from the weather change, we can also see progress on the timber roof as well as on the Domes.